Production done vs plan report

For production admin, planner +21 min readChecked 2026-11-26

For planners and managers. It compares, per item and period, what was planned, what was released as production orders, and what was actually made and rejected. Open Production › Reports › Done vs plan.

Read the report

  1. Choose By month or By week, an Item type and the From and To dates. The default is this month and the two before.
  2. Planned is the production plan lines by their week. Released is the quantity on orders (not draft or cancelled) by due date. Made and Rejected are the output recorded in the period, on the day it was recorded.
  3. Made vs released is made divided by released: green from 95 %, amber from 70 %, red below.
  4. The boxes add up everything shown. Export CSV downloads the rows.

Because output is counted when it is recorded, an order that finishes after its due date shows its output in the later period.